How Seattle’s Waterfront Plan Took Shape

See Seattle waterfront's milestones

By Erica C. Barnett February 25, 2019

Aquarium_Campus_New

This article originally appeared in the March 2019 issue of Seattle magazine.

[addtoany]

This article appears in print in the March 2019 issue and is part of our Seattle Waterfront feature. Click here to subscribe.

2001
February: Nisqually Earthquake occurs and damages the State Route 99 Alaskan Way Viaduct

2009
January: City, county and state governments agree to replace the Alaskan Way Viaduct with a tunnel

December: City forms Central Waterfront Partnerships Committee

2010
September: James Corner Field Operations (JCFO) selected to design Seattle’s waterfront park

2011
January: Seattle City Council creates Central Waterfront Committee (CWC); public outreach begins

2012
August: Seattle City Council adopts JCFO concept design and CWC strategic plan

Summer: Friends of Waterfront Seattle is incorporated

November: Voters approve bond for new seawall

2013
November: Seawall construction begins

July: Tunnel-boring machine “Bertha” begins work on the Viaduct replacement tunnel

December: Bertha stalls

2014
February: The city’s Office of the Waterfront is formed

August: Voters approve metropolitan park district to create sustainable funding source for Seattle parks

2015
March: City Council authorizes Pike Place Market MarketFront expansion

June: MarketFront expansion breaks ground

August: City Council and mayor approve master plan for aquarium expansion

December: Bertha resumes tunnel-boring work

2016
July: City Council approves Pier 62 rebuild

2017
April: Bertha finishes tunnel-boring work

June: MarketFront opens

August: City Council releases local improvement district (LID) feasibility study

September: City Council adopts a resolution affirming the LID funding approach for the waterfront

Fall: Groundbreaking for Pier 62 rebuild; seawall replacement project complete

2017–2018
City Council reaches out to property owners who would be affected by LID tax

2019
January: City Council considers LID legislation; Alaskan Way Viaduct is closed

February: The new State Route 99 tunnel opens

Late winter and spring: Alaskan Way Viaduct is removed

Follow Us

Chik-Fil-A and Starbucks, But No KFC

Chik-Fil-A and Starbucks, But No KFC

What’s your guilty fast-food pleasure?

Now comes a new data study that reveals Washington’s favorite and least favorite fast-food chains...

Virtual Playground

Virtual Playground

VR social gaming launches in Bellevue

Brush up on your VR gaming skills so you don’t flail in front of an audience — though, that’s meant to be part of the fun...

Downtown Seattle Gains Ground

Downtown Seattle Gains Ground

Foot traffic is on the rise

Downtown Seattle foot traffic continues to increase even though major retailers are increasingly moving out...

Canlis Goes Pink For KENLIS

Canlis Goes Pink For KENLIS

Upscale restaurant gets a colorful makeover

[addtoany]Canlis is going pink. The Seattle fine dining restaurant is ditching its dark colors in favor of a bold pink for a Barbie-themed event called “KENLIS” Aug. 9 and 10. The restaurant is now painted a flashy bright pink. The event is a dance party at “the Canlis dream house” that benefits breast cancer research…